Discovery Elementary School
on the Williamsburg Middle School Campus
Project Information:![school plan school plan]()
As a result of the APS system wide capacity and facilities studies, and through a rigorous feasibility study involving several current APS sites, a new elementary school for the Williamsburg Middle School (WMS) site was proposed and approved by the School Board.
In conjunction with the design for the new ES, Master Planning for the entire WMS campus will also take place. The Master Plan will look at future capacity and space planning for the middle school as well as site issues such as vehicular and pedestrian flow in and around the site and parking for the site.
Approximate square footage for the new ES: 97,000 SF
Approximate construction cost: $35M
Approximate total project cost (including soft costs and community amenities) $46.5M
Scheduled construction start: March 2014
Scheduled construction completion: Summer 2015
Architect: VMDO Architects
Updates:
- February 19, 2014, Community Meeting Presentation pdf
- December 5, 2013, School Board Final Design Presentation pdf
- September 21, 2013, County Board Use Permit Presentation pdf
- September 9, 2013, Planning Commission Presentation pdf
- September 5, 2013, Transportation Commission Presentation pdf
- Use Permit Application pdf (drawings available through Arlington County Zoning Dept.)
- Environmental Assessment pdf
- May 2, 2013, Schematic Design brochure pdf
- May 2, 2013, Schematic Design Presentation for School Board, Information Item pdf
- April 30, 2013, Gallery Walk for Public Review of Work Presentation
- February 7, 2013, Concept Design Presentation to School Board, Action Item pdf
- January 24, 2013, Concept Design Presentation for School Board, Information Item pdf
- Responses to questions/comments on Toole Design Group Transportation Study pdf
- January 17, 2013, School Board/County Board Joint Work Session APS Staff Presentation County Staff Presentation
- January 14, 2013, Gallery Walk for Public Review of Work Presentation
- Questions and Answers for 1/9/13 Community Meeting Presentation
- December 20, 2012, Update School Board on Building Site Design Monitoring Item Presentation
- No-build zones proposed by members of Rock Spring Civic Association
- Tool Design Group Responses to Comments on Transportation Study for New ES#1, 12/18/12 (PDF)
- Questions and Answers for 10/11/12 Community Meeting (PDF)
- Community Meeting on Traffic and Parking October 11, 2012 Presentation
- Neighborhood Meeting Sept. 13, 2012 Presentation
- Preliminary work - subsurface investigation
Studies/Examples of K-8 School Models
*****************************************
BLPC and PFRC Meeting Schedule
| SEPTEMBER | BLPC | PFRC |
| September 6, 2012 | ||
| September 12, 2012 | ||
| September 19, 2012 | ||
| OCTOBER | BLPC | PFRC |
| October 3, 2012 | ||
| October 10, 2012 | ||
| October 24, 2012 | ||
| October 25, 2012 | Joint School Board / County Board Meeting - Ashlawn ES | |
| NOVEMBER | BLPC | PFRC |
| November 7, 2012 |
| |
| November 14, 2012 | ||
| November 28, 2012 | ||
| DECEMBER | BLPC | PFRC |
| December 5, 2012 |
| |
| December 13, 2012 | CANCELED | |
| JANUARY | BLPC | PFRC |
| January 9, 2013 | OPEN BLPC Meeting | |
| January 17, 2013 | Presentation | |
| January 23, 2013 | Presentation | |
| FEBRUARY | BLPC | PFRC |
| February 13, 2013 | Presentation | |
| February 27, 2013 (TENTATIVE) | ||
| MARCH | BLPC | PFRC |
| March 19, 2013 | Presentation | |
| March 20, 2013 | ||
| APRIL | BLPC | PFRC |
| April 3, 2013 | Presentation | |
| April 17, 2013 | ||
| April 24, 2013 | Presentation | |
| MAY | BLPC | PFRC |
| May 1, 2013 | Presentation | |
| JUNE | BLPC | PFRC |
| June 26, 2013 | Presentation | |
| JULY | BLPC | PFRC |
| July 24, 2013 | ||
| July 31, 2013 CANCELED | ||
| SEPTEMBER | BLPC | PFRC |
| September 11, 2013 | ||
| NOVEMBER | BLPC | PFRC |
| November 20, 2013 | Presentation |